Solar Power Plant Installation processes are determined by assigning the optimum power of the energy generation plant to be installed after technical analysis, application documents are prepared according to the regulations and application is made to the relevant distribution company. Then, the processes continue as follows.
The optimum power to be installed is determined by conducting discovery and technical analysis and the relevant documents are prepared and an application is made to the distribution company.
Electrical and mechanical projects are prepared according to the products to be used in the system and submitted to the approval of the relevant institution.
After receiving project approvals from the relevant institution, an Agreement for Connection to the Distribution System for Unlicensed Electricity Producers is concluded with the distribution company.
After the preliminary acceptance, an application is made for TEDAŞ acceptance, the system is examined on site with the established committee and accepted by TEDAŞ and the system starts to generate energy legally.
After the acceptance of TEDAŞ, System Usage Agreement is signed with the Distribution Company and the active operation period is started by commencing production and consumption offsetting with the retail company.